Proposed improvements to capital investment and delivery under the National Development Plan

April 04, 2023

The Minister for Public Expenditure, National Development Plan Delivery and Reform, Paschal Donohoe, has announced various actions to enhance capital project delivery within the National Development Plan (NDP). The clear challenge lies in balancing the appropriate scrutiny needed for all capital projects and safeguarding public funds in a way that is not burdensome or time-consuming. These reforms to the Public Spending Code (PSC) seek to safeguard the robust, transparent and considered oversight of public funds while streamlining the process and introducing efficiencies. The Minister will take a more direct role in overseeing NDP delivery by chairing the Project Ireland 2040 Delivery Board.

Business professionals discussing a document.

The PSC is the Government’s framework for spending public funds. The capital spending version of the PSC is a set of rules and guidelines that seek to successfully deliver projects which provide benefits and outcomes aligned with government policy and offer value for money. For example, if the objective is to reduce carbon emissions in transport, one way would be to increase public transport provision through more buses, trains, trams and improved infrastructure. Each of these measures requires Government investment—that’s where the PSC comes in.

In broad terms, a business case is produced that estimates the costs and benefits associated with a project and recommends a preferred course of action. This preferred course of action is then progressed to delivery (e.g. via the procurement of a contractor and/or operator).

In the past, business cases were treated by many as a box-ticking exercise. Little heed was given to them or their projections, as the focus was mainly on getting the project going. This worked in some instances and helped quicker delivery. However, in other cases, there were significant issues with delayed projects, running over budget or failing to achieve the intended benefits. The most high-profile case is the New Children’s Hospital. In 2019, PwC concluded an independent report for the Government on the escalation of costs on that project. It found a perfect storm of issues associated with the project including poor forecasting, a lack of understanding of the risk profile associated with the project, a lack of commercial capability and accountability gaps in governance.

The recommendations in this report informed the 2019 update to the PSC, which sought to address the failings at the New Children’s Hospital and ensure lessons are learnt for future projects. These updates brought more up-front thinking to capital project appraisals. This welcome development meant that Government Departments and agencies tasked with delivering capital projects would have to do more work up-front to understand costs, risks and benefits to apprise projects robustly. It also focused on improved governance, increasing accountability in departments and at cabinet, as well as detailed analysis of procurement approaches before a project is approved.

These changes made sense on paper. However, they created challenges when rolled out across the public sector. The changes were not dramatic for some departments and agencies as they had applied similar rigour in the past. For others, it was a dramatic shift and a number are still getting to grips with the changes. In addition, heightened levels of assurance and review were introduced for major projects (i.e. those over €100m). This added robustness (see the Major Projects Advisory notes to date) but also lengthened the time taken to commence delivery. In the period since 2019, Government capital expenditure allocations have increased by 70%—from €7.3bn in 2019 to €12.4bn allocated for 2023.

Delays are costly; the longer it takes to deliver capital projects, the less chance we have of achieving our policy targets and further dis-benefits or costs start to emanate. This is most acutely felt in housing and health but is also evident in energy and transport, where we are now at risk of not decarbonising quickly enough.

In 2023, we have the policy direction through the NDP and the Climate Action Plan. We have the framework to deliver through the PSC, and we have the funding allocations from the Government as well as private finance for areas such as renewables. So why aren’t we delivering?

Put simply, we do not have sufficient capacity and capability in the public sector or agencies to deliver. The stepped increase in funding coupled with increased up-front work on projects has created a need for more public sector staff, including project directors and multidisciplinary teams with infrastructure experience driving these projects and programmes forward. There’s also a need for further transparency and sharing of information, knowledge and lessons learnt across agencies and departments.

The announcement last week from Minister Paschal Donohoe which outlined various actions seeking to improve the progress of capital delivery under the NDP is a welcome development. In particular:

  • the increased focus on accountability, with the Minister joining the Project Ireland 2040 Delivery Board and associated reporting on the progress of projects; and
  • the capacity reviews of departments and agencies to ensure adequate and appropriate resources and capabilities.

Other PSC reforms include:

  • the introduction of infrastructure guidelines with approval stages reduced from five to three; and
  • ongoing reforms to public works contracts under the Capital Works Management Framework (CWMF).

Details on the new guidelines have yet to be set out, but the principle of up-front thinking and analysis must be maintained to increase the probability of a smooth and efficient project delivery.

The balance of risk in public contracts has proven challenging in recent years. The approach of procuring fixed-price contracts through the CWMF and expecting contractors to accept full project risks has led the market to reconsider bidding on contracts, especially the more complex and higher-value ones, or factoring high risk premiums into the price. We recommend further reform, including facilitating more collaborative contracting and risk-sharing where risk is allocated to the party best suited to manage it.

Finally, the actions include an independent evaluation of NDP priorities and capacity, which will be conducted over the coming months. This independent assessment is welcome and will be critical in understanding what needs to be delivered and how much needs to be spent. At present, some of the figures that build up to the €165bn in the NDP are not fully developed or fully reflective of the capital funding required. In addition, in the last year, inflation has diminished the purchasing power of the allocated €165bn, which will continue as long as inflation remains above zero.

All in all, we are on the right track in setting policy targets across sectors and making funding available. The focus on up-front thinking and analysis should be maintained and supported by investment in skilled resources to progress delivery.

We are here to help you

As these changes to the public spending code continue to unfold, you will face challenges in progressing your capital projects through the decision gate process given the current uncertainty. Given our experience working with public and private sector clients on a broad spectrum of capital projects, we are ideally positioned to assist you in navigating these changes.

Contact us

Robert Costello

Partner, PwC Ireland (Republic of)

Tel: +353 (87) 636 4014

Gillian Hegarty

Director, PwC Ireland (Republic of)

Tel: +353 (87) 241 3927

Peter Carrigy

Manager, PwC Ireland (Republic of)

Tel: +353 (87) 167 3077

Follow PwC Ireland